Due to delays, Karnataka has requested an extension of the Phase II deadline beyond March 31, 2026, in order to expand its transmission network for renewable energy under the Green Energy Corridor project.
The main obstacle to the project, which aims to construct specialized infrastructure to transfer renewable energy from sources like wind and solar into the national grid, is the difficulty of acquiring property, especially when it comes to obtaining right of way for transmission lines and substations.
Execution delays slow progress
Only roughly half of the project’s implementation has been finished by the Karnataka Power Transmission Corporation Ltd. By the end of March 2026, about 498 circuit kilometers of 600 MVA transmission lines and substations had been put into service, compared to a target of 938 circuit kilometers and 1,225 MVA. The system is designed to facilitate the evacuation of approximately 2,640 MW of renewable energy.
Citing several obstacles that have impacted schedules, the state government has asked for an extension until July 31, 2027. These include certain transmission component delays and the requirement for new surveys in certain areas because of expected right-of-way problems.
The estimated overall cost of Karnataka’s share of the project is Rs 1,036 crore, of which the Center will contribute around 33 percent. Rs 108 crore has been paid out thus far. Over Rs 11,000 crore would be invested in the larger Green Energy Corridor scheme, with the majority of the cost to be covered by the states.
FAQs – Green Energy Corridor Project in Karnataka
Q1. Why has Karnataka requested an extension for the Green Energy Corridor project?
Karnataka has sought an extension beyond March 31, 2026, due to delays in execution and challenges in expanding its renewable energy transmission network.
Q2. What is the main reason for delays in the project?
The biggest obstacle is land acquisition, especially securing right of way for transmission lines and substations, along with survey and execution delays.
Q3. How much progress has been made in Karnataka’s Phase II project?
Only about half of the targeted infrastructure has been completed so far, with 498 circuit km of transmission lines commissioned against the target of 938 circuit km.
Q4. What is the purpose of the Green Energy Corridor project?
The project aims to strengthen infrastructure for transferring renewable energy from solar and wind sources into the national power grid.
Q5. How much renewable energy capacity will the project support?
The system is designed to evacuate approximately 2,640 MW of renewable energy once fully completed.
Q6. What is the revised deadline requested by Karnataka?
The state has requested an extension of the deadline until July 31, 2027.
Q7. What is the total cost of Karnataka’s share in the project?
Karnataka’s portion of the project is estimated at ₹1,036 crore, with around 33% funded by the central government.
Q8. How much funding has been released so far?
Approximately ₹108 crore has been disbursed to support the project.
Q9. What is the overall investment in the Green Energy Corridor scheme?
The broader project involves an investment of over ₹11,000 crore, with most of the funding borne by state governments.





